Tuesday, August 5, 2008

From the desk of...Patti Flaherty:

A quick update on how things are progressing at the Lake Country Learning Community construction site.


The construction time line is moving along well at this stage in the game. We are still planning on a gradual and partial opening that will start in early December 2008. The construction and development world is very unpredictable however we are guardedly optimistic that we will meet this time line. We will be sure to update you as this date and time line become more certain or if it is likely to change.

A few highlights include:
Siding has started and is about 40% complete;
Insulation is essentially complete for the first 2 of the 6 homes;
Dry walling has started in the first 2 homes;
Electrical and mechanical work is well on their way to completion;
Framing is less then a week to completion for the entire development;
Geothermal drilling begins next week;
Interior design concepts for all 6 homes and the common areas are complete.