Wednesday, October 29, 2008

We've got color!!



A quick update on how things are progressing at the Lake Country Learning Community from Patti Flaherty. Construction is moving along pretty well. We are still on track for a partial opening in December – we are shooting for the week of December 8th.
Construction Update Highlights:


  • The first 2 homes are being painted;
  • Millerwork/cabinetry and flooring will begin next week;
  • The geothermal system is moving along – the drilling (90 holes at a depth of 220 feet) should be complete by Oct. 29th – a huge undertaking;
  • We should have heat and electricity in the building by the 2nd week of November; Site is being prepared for landscaping this week and landscaping will begin once the drilling for the geothermal system is complete;
  • Off site work (curbs, gutters and other civil work) will begin later this week if all goes well;
  • Mid to late November we should have full access to the first home to move in furniture and make it a home!!
Completion Timeline: Partial occupancy in December open either 1 or 2 of the homes; Mid to late January homes #3 and 4 will be ready for occupancy; Mid to late February the construction should be substantially complete.

Operational Plan:
Begin the IH Residential Contract the week of December 8th (we are working closely with Deb Preston and her team to work out the details and schedule); Begin the IH Transitional Rehabilitation Contract the Week of either January 12th or 19th – to be confirmed – (we are working with Darlene Arsenault, Lori Seeley, Faye Burch, Deb Preston and Harry Miller (and others behind the scenes) to confirm timelines, referral processes and admission criteria etc.); By the end of February we should be fully open with capacity for 42 units (28 to serve the 2 IH contracts and 14 for private contract) to serve the brain injury population.